AGO6
Station Report
2000-2001 Summer
UT Day 319 - 347
On-site personnel:
Kevin Killilea, Ty Milford. (Field personnel/Groomer)
and Todd B. Johnson (AGO engineer) comprised the service crew for the AGO-6
2000 season.
Station:
The station was cold upon arrival, had
a strong smell of propane, and the emergency shut-off valve had activated.
There was a 10-pound stack of ice on the exhaust shroud and a 3-inch plug
of ice had formed inside the air filter. The nitrogen tank was not turned
on, which left propane vapor pressure as the only force pushing fuel into
the station. Propane boils (vaporizes) at -44 C, so at temperatures colder
than -44 C, there was not enough pressure to push propane into AGO-6.
The following chain of events may have
contributed to station shut down:
1) The AGO Team failed to turn the nitrogen
on.
2) The outside temperature dropped to -48.8
C on June 17, 2000, the day the station shut down. Propane could not vaporize
at this temperature, the force pushing the fuel into the station into the
station dropped, and TEG starved for fuel.
3) As fuel starvation continued, burner
temperature decreased to the point where the igniters turned on. The igniters
placed a large load on the TEG/Turbo batteries and drained them.
4) As the TEG temperature drops, the amount
of heat transfer to the freon and exhaust shroud decreases. The TEG exhaust
(carbon dioxide and water vapor) passing through the cold shroud condenses
and freezes, causing the ice plug.
5) The propane shut-off valve is designed
to close at -20 C. As much as three days may elapse between station shut-down
and the interior cooling to -20 C. During this time, propane is still being
delivered to the TEG and not being burned. This would account for the strong
odor of ethyl mercaptan in the shelter. The air filter and the exhaust
stack, which were blocked, slowed the escape of the propane.
The technical service team easily started
the TEG, used fuel left in the main tanks, and raised the station temperature
to 20-25 C. That temperature was maintained throughout the service call.
AGO-6 was approximately 2 feet above the
surface and the wind effects created a bowl-shaped hole about 4-5 feet
under the bottom of the station. The support posts were pulled out of the
ice, new footers were placed, and the AGO was raised to its maximum height.
The corner guy wires were reattached at the base only. The upper guy wires
were not necessary for the stabilization of the site. One complete cable
set with deadmen are on the site for next season. New footers will be needed,
however.
TEG:
The TEG Turbo was modified to allow it
to extract power directly from the PSC. The priority of the turbo was reset
to the highest priority for power use at the station. New batteries for
the turbo were installed. Batteries for the electronic shutoff valve were
also replaced. The manifold propane pressure is set at 3.0 psi. Maximum
burner temperatures that could be reached were well above 300 C, but burner
temperatures were set between 295 C to 300 C. Freon pressure was maintained
at 20 psi. At burner temperatures of 300 C, freon pressure is 24 psi. Aluminum
baffle plates were installed above the vertical air fins to restrict air
movement through the internal TEG heat exchanger.
Data Control Unit (DCU):
Two Storage computers (Rev 2, SN: 00-011
and 00-012) were installed in the DCU. The old storage computers were removed
and will be shipped to Augsburg College for data retrieval and processing.
Power Supply Controller (PSC):
All functions of the PSC were normal when
it initially powered up. All channels were checked and worked effectively.
After the PSC and DCU were activated, power was delivered to all experiments.
The BAGOEXP board was updated with PIC TIPIC002 rev. 04. See AGO6.AGO for
experiment power settings, priorities, and other station information.
Data Acquisition Unit (DAU):
All functions were normal when the unit
was turned on. Non-volatile random access memory was installed in the DAU
and the DAU software was upgraded to Rev. 3. See AGO1.AGO for DAU settings.
Global Positioning System Receiver (GPS):
The GPS was functional when the AGO electronics
were turned on.
Bell Labs Fluxgate Magnetometer:
Data was examined to verify the operation
and leveling of the magnetometer. The magnetometer needed re-leveling,
which was done on day 346. The box containing the sensor remained in its
original position and the cover for the vault was raised to the surface
and marked with flags.
Current settings for the magnetometer are:
Sensitivity : 1000 nT
H Offset : + 00 02 794
D Offset : OFF 00 00 000
Z Offset : - 03 02 850
The electronics were checked out per the
servicing documentation. The results of the initial checkout were faulty
due to the magnetometer not being level. The magnetometer was leveled and
the D axis was zeroed, the data collected is as follows:
Axis Meter Out DAU
Reading Reading
H: -10.000 V 0005 Hex.
+ 0.000 V 0800 Hex.
+10.000 V 0FF6 Hex.
D: -10.000 V 0035 Hex.
+ 0.000 V 0800 Hex.
+10.000 V 0FFF Hex.
Z: -10.000 V 0001 Hex.
+ 0.000 V 0800 Hex.
+10.000 V 0FF9 Hex.
Tohuku ULF Search Coil:
The search coil experiment data showed
variance in relation to data collected the previous year. The experiment
receiver was examined and there was a noticeable change to the readings
on the front panel when the lamp was engaged. Meter readings would not
return to their original position when the lamp switch was engaged or disengaged.
The unit was replaced and data was examined. Data in the new unit resembled
that of the previous year. The overall system was determined to be operational
and functionally sound. Sample data from the old unit was collected and
stored to the laptop prior to the instrument being replaced. Data was being
collected from the new unit but was unsuccessfully recorded because the
team ran out of time on the pull out.
University of Maryland Riometer:
The riometer vault was partially dug out
3-4 feet this season. The 12-foot flags indicating the vault location were
exposed a foot above ground, so about 8 feet of digging remains. The hole
is covered and marked for continued effort next year. Additional digging
equipment will be brought to excavate a hole 12-feet deep through an area
crossed by cables. Sample riometer data was collected prior to the resupply
flight and stored to the laptop.
Dartmouth LF/HF Receiver:
Dartmouth was upgraded for a data rate
of 40 samples per second. Data was collected and examined then stored on
the laptop.
Allsky camera:
The Allsky camera upgrade was completed
but sample data was not obtained. The service team pulled out before the
data could be saved.
Miscellaneous:
GPS position: S 69 31' E 130 02'. Elevation:
2343 m.
Notes for the future:
1) The Riometer experiment needs an extension
cable to connect the old cable to the station electronics. The old cable
is stretched tight after raising the AGO.
2) Whenever a power source or experiment
has been modified, it should be tested for greater than 1 MOhm isolation
to chassis BEFORE the unit is connected to the PSC. The PSC is very
sensitive to violations of this specification.